3rd Floor Framing (2016-05-08)

i-beams

The 3rd floor is the most advanced in the building, with lofts units being framed-out rapidly. While it’s still early, the high ceiling heights and beauty of the i-beams are now evident. The sub-floor-boards will be exposed in the ceilings.  Click to enlarge. Photos by Barbara Hatch

Clerestory

Clerestory

  The 4th floor of Roebling Lofts will be an extraordinary place to live, as is becoming evident in this construction photo. Most of these units will be two bedroom. The steel trusses will be exposed, and every unit will get light from these clerestory windows, with 16-24′ ceilings.

2016-04-25 Construction Photos

Corridor Framing

As of late April, the subfloor replacement on floors 2-4 has continued.  New, the roof deck is now being installed.  Also, on the third floor you can see the first evidence of interior framing:  the corridor with entrance doors is now being demised.

Construction Trades Job Fair – May 6, 1-4 PM

Cumby Logo

W.S. Cumby, Builders and Construction Managers, will be hosting a Job Fair for residents of Trenton, NJ on Friday May 6, 2016 from 1:00PM to 4:00PM at the site of the future Roebling Lofts, 71 Clark Street, Trenton, New Jersey 08611. The purpose of the job fair is to provide employment opportunities to residents of […]

Nora Muchanic Reports on Roebling Center!

Nora Mechanic

Recently, Channel 6’s much-loved NJ affairs reporter, Nora Muchanic, paid a visit to the Roebling Lofts site and interviewed the three HHG principals who are responsible for the project. We had fun, and so it seemed did Nora! Check it out!

2016-03-03 Groundbreaking

Groundbreaking shovels

March 3 was the official groundbreaking for Roebling Lofts. The Honorables Brian Hughes (Mercer County Executive) and Eric Jackson (Mayor of Trenton) showed up to speak and shovel some dirt. Click on an image to view it full size in light box

Construction Update #1

Porta potties on site

Well, if anyone doubted that construction would start, look no further than this photo: the porta-potties have arrived! OK, so the construction fencing has gone up as well! Watch this page for the latest news of ongoing construction, which will start with clean out and replacing the sub-floors.

Roebling Lofts Financed!

Fulton-and-TBoP-announcement

(January 27, 2016) HHG Development Associates, LLC announced today that its financing for Roebling Lofts has been completed. Fulton Bank of NJ will be leading the investment, providing construction debt, long-term debt, and tax-credit financing. The Bank of Princeton will be participating in the construction and long-term debt financing. “We’re thrilled to complete this essential […]