January 4, 2017, we’re opening a temporary Leasing Office in a trailer on-site. We anticipate the first lofts will be occupied in March of this year. How is that possible? Well, behind those temporary windows there’s a LOT going on!
- Slowly, the temp windows are being replaced with the gorgeous, real ones. Here’s a 3rd floor Otis unit.
- Here’s the same Otis unit, looking the other way. Note most doors are hung. Tile is stacked about to be laid.
- A Brooklyn unit with tile floor laid, and cabinets going in. 3rd floor, north. one of the first units to open…
- Close up of a tile floor!
- Here’s the bathroom. Tub and tile are in!
- Over a hundred workmen are employed on a busy day. Here’s someone hanging doors in a Neversink unit.
- Pouring gypcrete sound insulation, south end of 3rd floor. These units will be ready about a week after the north end.
- Electricians wiring a GWB unit on the 2nd floor. May availability
- Framing the Williamsburg II unit on first floor. June availability.
- Ria, the building manager, getting a computer ready in the temporary leasing office. Come by! You’ll see it transformed.