Work across the entire project is going well. The 3rd floor is most advanced, with many units now framed out, and spiral stairs installed. Plumbing, electric, sprinklers, and other systems are going in rapidly. Just behind the 3rd floor, is the 4th, with truly dramatic, mostly 2-bedroom units, going in. Very cool!!
- Progress! Temp windows on 3rd floor to keep out the rain while finish work continues
- Spiral stairs from sleeping platform.
- Framed 3rd floor unit showing stairs installed
- Scaffolding on 4th floor for masonry restoration
- Masons just getting started on 4th floor (interior view of scaffolding just shown)
- 4th floor view from NW corner
- Sound insulation going in near 4th floor clerestory
- Sheet-rocking 4th floor below clerestory
- Utilities and drain pipes getting buried in preparation for pouring floor